Total megawatts of U.S. nuclear capacity offline right now (units in outages plus reduced power).
13,804
MW Offline
Percentage of total fleet capacity currently online and generating power.
85.7%
Fleet Online
Refueling outages scheduled for this season. Each one is a hiring window.
24
Fall 2026 Outages
Units currently at 0% power (likely in an outage or shutdown).
13
Units Offline
Units operating between 1-99% power (excluding known startups or coastdowns).
3
Reduced Power
Units nearing the end of their fuel cycle, gradually lowering power before an outage.
2
Coastdown
Units increasing power following an outage or scram.
0
Starting Up
Units on a qualifying Breaker-to-Breaker run: continuous operation exceeding their cycle-adjusted threshold with no trips to 0% power.
5
Breaker-to-Breaker
Nuclear NewsNEW 85-kW MARVEL microreactor gets liquid-metal coolant ahead of criticality test85-kW MARVEL microreactor nears criticality as coolant arrives Engineers at Idaho National Laboratory integrated a new liquid-metal coolant vessel and secured federal safety approval for the Department of Energy project. The team scheduled initial low-power physics tests for December to collect baseline operational data from the compact system. DOE's MARVEL microreactor is entering a new testing phase after a key coolant vessel milestone and federal safety approval. A small nuclear reactor at Idaho National Laboratory is approaching its first criticality test after engineers received its primary coolant vessel. The primary coolant vessel for the Department of Energy’s MARVEL microreactor reached INL in mid-September. Its arrival gives engineers another major component to integrate before t...
Nuclear NewsNEW Furnace StartupOperators at the Y-12 National Security Complex completed the initial test firings of sintering and microwave casting furnaces within the Uranium Processing Facility. This testing program advances efforts to modernize national uranium processing capabilities for future operations. Technicians will review initial data and prepare for surrogate material testing before bringing the equipment to full operating temperatures. The Uranium Processing Facility (UPF) Project recently made history by starting up furnaces for the first time, making a major milestone in modernizing the nation's uranium mis...
Nuclear NewsNEW Another nuclear company chooses Oak Ridge for headquarters as industry continues to growAmentum has relocated its global nuclear operations headquarters to Oak Ridge, Tennessee. The facility will house over 150 specialists focused on nuclear growth and environmental remediation projects. The relocation highlights the concentration of nuclear sector infrastructure and workforce development programs in East Tennessee. The company also established scholarship partnerships with local educational institutions to support the pipeline of technical workers for future projects. Amentum moves its nuclear operations headquarters to Oak Ridge, Tennessee, joining over 150 experts to support U...
Site NewsNEW Our long-range outage projections just got sharperNukeWorker's Outage Schedule gives you two things: validated dates for the coming season, and our own long-range projections for the seasons beyond, 18 to 24 months out, before the utilities publish their dates.Today we upgraded the engine behind those long-range projections. Measured against the dates utilities have since confirmed, the new engine is 28% better at predicting long-range (18 to 24 month) start dates.See how we score ourselves on the Accuracy Scorecard.
Fallen:NEW Roger SlocumRoger passed away recently. He retired from Oconee after 46 years and then came back and worked some more. Roger was a long time Rad tech and ALARA planner. A great many people are very sad right now. He will be missed.
Outage NewsNEW Palo Verde 1 begins Fall 2026 refueling outagePalo Verde Unit 1 began a routine refueling outage on October 3, 2026, starting exactly on its scheduled date. The 1,311-megawatt pressurized water reactor enters the maintenance period following a 1,270-day unscheduled-outage-free streak. Operated by Arizona Public Service, the unit had completed about 93 percent of its typical 548-day operating cycle and recorded an 87.8 percent capacity factor during the 2025 cycle. The 45-day scheduled duration compares against a 42.4-day historical average across 18 prior refuels for the plant. Across the broader U.S. fleet, 94 units operated at an 85.4 percent capacity factor, with 12 units currently in refueling outages. TONOPAH, AZ. Refueling activities began at Palo Verde 1 on Oct 3, 2026 . The unit started on the published date (Oct 3, 2026) with...
Outage NewsNEW Salem 1 begins Fall 2026 refueling outageSalem 1 began a routine refueling outage on October 4, 2026, starting precisely on its planned date. The PSEG Nuclear plant has a scheduled duration of 50 days for this maintenance period. The 1,153-MW Westinghouse 4-loop pressurized water reactor entered this refueling outage after maintaining a 624-day unscheduled-outage-free streak. Salem 1 had run about 90 percent of its typical 549-day operating cycle following an 85 percent capacity factor during its 2025 cycle. PSEG Nuclear operates two other United States nuclear units, while the broader nuclear fleet records an 85.2 percent capacity f...
Outage NewsNEW McGuire 1 completes Fall refueling outage in 29 daysMcGuire 1 began a routine refueling outage on September 5, 2026, concluding after 29 days on October 3. The fall maintenance window ran one day longer than the planned 28 day schedule. Operated by Duke Energy Carolinas, the 1,158-MW Westinghouse pressurized water reactor maintained an unscheduled-outage-free streak of 246 days before the project. The duration ranked as the 13th-longest among the unit's 19 tracked refuels, falling below the historical average of 37.6 days for its 18 prior refuels. Across the broader U.S. fleet, 94 units operated at an 85.2 percent capacity factor while four oth...









Our long-range outage projections just got sharperNukeWorker's ...
Every Outage Finally Has a NameIf you have worked an outage, you know it has a name. Nobody at the tool crib says &qu...
New on the facility map: see who's hiring at a glanceThe facility map got a pretty good overhau...
Did You Know NukeWorker Has Online Practice Exams? (Now With Certificates)Here is something a lot of folk...
The NukeWorker Reactor Status MapIf you have ever wanted to know which plants are running, which are down for an outa...
We have recently updated the with over 1,500 new aerial and facility images.Some of the late...
The Fall 2026 U.S. nuclear refueling outage schedule has been released. 25 units are scheduled to refuel this season.
POET: plant-specific PRA inputs, built from the operating recordA new tool on NukeWorker turns the U.S. fleet's...
We've launched a new board, Outage News: a running record of refueling and forced outages across ...
New Feature: RadNet Radiation Map Now OnlineWe're excited to announce a major addition to the Facility Info...
We have updated the "Current Reactor Status" section on our facility information pages ...
🔎 Deep Dive: Everything You Can Track on the Facility Info PagesHey everyone, I've been digging thr...
The Nuclear Grid Capacity & Generation Analysis dashboard provides a centralized interface for monitoring and...
We made a new tool fro you:The Operating Reactor Scram Dashboard is a comprehensive analytical tool designed fo...
I am very excited to announce a major upgrade to the NukeWorker Outage Schedules!We now independently project...
NukeWorker's preliminary schedule for Spring 2027 projects 29 nuclear outages, signaling a high-d...
The Fall 2026 nuclear maintenance season features 25 scheduled outages, with peak workload activity proje...
The Spring 2026 nuclear outage season is underway with 34 scheduled maintenance and refueling outages. View the full schedule at .
We've given the entire quiz section a major facelift to make your study sessions smoother and easier on the eyes.
The NukeWorker Photo Gallery has long been the primary destination for our community to share the history, te...
We've just rolled out a major update to the NukeWorker homepage. While the new "Situation Room&quo...
I split the 'Nuclear Discussions' from the 'Nuclear News' posts on the front page.Enhanced the titl...
I've updated the homepage Job Feed with a few key features designed to make it fairer for employers and easier for ...