D.C. Cook 1 - Plant Information & Status

Technical specifications, contact data, ratings, and licensing history for the D. C. Cook facility.

Ratings 105 votes

?
Community ratings from NukeWorker members. Vote to share your experience working at this facility. Results show the breakdown of Above Average, Average, and Below Average ratings.

Capacity Factor (365-Day)

100%
Current
92.5%
365-Day Avg
#34
of 94 plants
Min: 0% Max: 100% 28 days <80%

Scram History 4 events since 2011

4
Total
2
Automatic
2
Manual
5
Avg Recovery (days)
Recent Events
2022-08-27 Auto AUTOMATIC REACTOR TRIP DUE TO REACTOR COOLANT PUMP TRIP The ...
2022-05-23 Manual EN Revision Imported Date: 5/25/2022 EN Revision Text: MANUA...
2014-10-31 Manual DUAL UNIT MANUAL REACTOR TRIPS DUE TO LOWERING CONDENSER VAC...
2011-09-06 Auto AUTOMATIC REACTOR TRIP FOLLOWING MAIN TURBINE TRIP FROM 100%...

Performance Charts

Outage Duration Trend

?
Scheduled refueling outage durations over time. Green bars are below average, yellow near average, red above. Dashed line shows the plant's historical average. Shorter outages mean better execution.

Power History (12-Month)

?
Daily power output as a percentage of rated capacity over the past 365 days. Green segments indicate full power (90%+), yellow shows reduced output, and red indicates significant power reductions or shutdowns.

Outage Timeline

?
Visual timeline of all recorded outages. Blue bars are scheduled refueling outages, red bars are forced/unplanned outages. Width represents outage duration. Hover for details.

Facility Statistics

Lifecycle & Tenure
Operating Age: 50.6 Yrs
Build Time: 6.4 Yrs
Lic. Remaining: 8.6 Yrs
Production & Power
Lifetime CF: 78.1%
Efficiency: 30.5%
Generated: 188.2 TWh
Reliability & Outages
Record Run: 673 Days
Refuelings: 16

Ownership & Construction

Owner/Operator: Indiana Michigan Power
Architect Engineer: AEP
Constructor: AEP

Technical Specs

Reactor Type: PWR
Containment: PWR-ICECND
NSS Supplier: WEST 4LP
Thermal Power: 3304 MWt
Net Capacity: 1009 MWe
Efficiency: 30.5%
Status: Operating

Licensing

Docket #: 05000315
License #: DPR-58
License Type: OL-FP
Const. Permit: 1969-03-25
Operating Lic: 1974-10-25
Commercial Op: 1975-08-28
License Renewed: 2005-08-30
License Exp: 2034-10-25

Facility Map

41.9754, -86.5652

Location & Contact

Address:
1 Cook Place
Bridgeman, MI 49106, USA
Get Directions
Phone: (269) 465-5901

Breaker-to-Breaker Runs 5 runs

?
Breaker-to-breaker runs measure continuous operation between refueling outages (470+ days). An active streak means the unit has been running continuously since the last refueling. Longer runs indicate better reliability.
517
Best Run (days)
2011-10-27 → 2013-03-27
500
Avg Run (days)
All Runs
2023-11-16 2025-03-22 492 days
2019-05-10 2020-09-19 498 days
2016-04-29 2017-09-13 502 days
2013-05-20 2014-09-24 492 days
2011-10-27 2013-03-27 517 days