Nine Mile Point 1 - Plant Information & Status

Technical specifications, contact data, ratings, and licensing history for the Nine Mile Point facility.

Ratings 31 votes

?
Community ratings from NukeWorker members. Vote to share your experience working at this facility. Results show the breakdown of Above Average, Average, and Below Average ratings.

Capacity Factor (365-Day)

100%
Current
99.2%
365-Day Avg
#39
of 94 plants
Min: 3% Max: 100% 5 days <80%

Scram History 11 events since 2011

11
Total
8
Automatic
3
Manual
7.7
Avg Recovery (days)
Recent Events
2019-04-28 Manual MANUAL REACTOR SCRAM DUE TO POWER OSCILLATIONS AND HIGH PRES...
2019-04-13 Auto AUTOMATIC REACTOR SCRAM AND SPECIFIED SYSTEM ACTUATION "On A...
2017-09-05 Auto AUTOMATIC REACTOR SCRAM ON LOW REACTOR VESSEL WATER LEVEL "O...
2017-03-19 Manual MANUAL SCRAM DUE TO PRESSURE OSCILLATIONS "On March 20, 2017...
2016-12-09 Manual MANUAL REACTOR SCRAM DUE TO HIGH MAIN TURBINE VIBRATIONS "On...
2015-09-03 Auto UNPLANNED AUTOMATIC SCRAM AND SPECIFIED SYSTEM ACTUATIONS DU...
2012-11-02 Auto AUTOMATIC SCRAM ON LOW REACTOR WATER LEVEL "On November 3, 2...
2012-10-28 Auto RPS ACTUATION WHILE CRITICAL DUE TO GENERATOR LOAD REJECT On...
+3 more events

Performance Charts

Outage Duration Trend

?
Scheduled refueling outage durations over time. Green bars are below average, yellow near average, red above. Dashed line shows the plant's historical average. Shorter outages mean better execution.

Power History (12-Month)

?
Daily power output as a percentage of rated capacity over the past 365 days. Green segments indicate full power (90%+), yellow shows reduced output, and red indicates significant power reductions or shutdowns.

Outage Timeline

?
Visual timeline of all recorded outages. Blue bars are scheduled refueling outages, red bars are forced/unplanned outages. Width represents outage duration. Hover for details.

Facility Statistics

Lifecycle & Tenure
Operating Age: 56.3 Yrs
Build Time: 4.6 Yrs
Lic. Remaining: 3.4 Yrs
Production & Power
Lifetime CF: 91.5%
Efficiency: 33.6%
Generated: 135.6 TWh
Reliability & Outages
Record Run: 728 Days
Refuelings: 14

Ownership & Construction

Owner/Operator: Constellation Energy
Architect Engineer: NIAG
Constructor: S&W

Technical Specs

Reactor Type: BWR
Containment: BWR-MARK 1
NSS Supplier: GE 2
Thermal Power: 1850 MWt
Net Capacity: 621 MWe
Efficiency: 33.6%
Status: Operating

Licensing

Docket #: 05000220
License #: DPR-63
License Type: OL-FP
Const. Permit: 1965-04-12
Operating Lic: 1974-12-26
Commercial Op: 1969-12-01
License Renewed: 2006-10-31
License Exp: 2029-08-22

Facility Map

43.5206, -76.4078

Location & Contact

Address:
348 Lake Road
Scriba, NY 13126, USA
Get Directions
Phone: (301) 415-8200

Breaker-to-Breaker Runs 4 runs

?
Breaker-to-breaker runs measure continuous operation between refueling outages (470+ days). An active streak means the unit has been running continuously since the last refueling. Longer runs indicate better reliability.
701
Best Run (days)
2021-04-11 → 2023-03-13
674
Avg Run (days)
All Runs
2023-04-20 2025-03-17 697 days
2021-04-11 2023-03-13 701 days
2019-05-06 2021-03-22 686 days