Prediction Explanation: Arkansas Nuclear 1

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 532.0 +26.47 days
Prior Cycle Length (months) 17.5 -13.58 days
Years to License Expiration 7.1 +3.41 days
Reactor Type (NSSS) B&W LLP -3.37 days
Years Since Major Maintenance 9.6 -2.14 days
Fleet Outages This Year 1.0 -1.66 days
Day of Week 6.0 +1.39 days
Net Capacity (MWe) 833.0 -1.3 days
Fleet Density N/A -1.03 days
m6_month_dist_to_modal 6.0 +1 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?