Projection Explanation: D.C. Cook 2
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
546.0 |
+13.99 days |
| Containment Type |
PWR-ICECND |
-8.38 days |
| Architect-Engineer |
AEP |
+8.29 days |
| Reactor Type (NSSS) |
WEST 4LP |
-4.53 days |
| Years to License Expiration |
10.8 |
-2.14 days |
| Fleet Density |
N/A |
+2.11 days |
| Avg Coastdown Days (this unit) |
4.1 |
-1.33 days |
| Month |
3.0 |
+1.24 days |
| Forced Outage Days in Cycle |
3.0 |
-1.11 days |
| Units at Site |
2.0 |
-1.06 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?