Projection Explanation: Fermi 2

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 730.0 -45.86 days
Containment Type BWR-MARK 1 +27.48 days
Reactor Type (NSSS) GE 4 +7.31 days
Avg Outages Between Major Maint. 2.0 -5.7 days
Units at Site 1.0 +4.65 days
State MI +2.47 days
3-Outage Rolling Avg Duration 62.7 +1.8 days
Prior Cycle Length (months) 24.0 +1.29 days
Fleet Outages This Year 1.0 +1.18 days
Balancing Authority MISO -1.15 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?

Page created in 0.005 seconds with 0 queries.