Prediction Explanation: Oconee 2

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Prior Cycle Length (months) 24.1 +30.06 days
Cycle Length (days) 731.0 -29.92 days
Years Since Major Maintenance 22.1 +1.98 days
unit_pct_in_predicted_month 0.6 +1.72 days
Containment Type PWR-DRYAMB -0.9 days
Reactor Type (NSSS) B&W LLP -0.74 days
Forced Outage Days in Cycle 0.0 +0.66 days
unit_pct_in_spring_fall 1.0 -0.66 days
Fleet Sequence Position N/A -0.62 days
Age at Outage (years) 53.1 +0.44 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?