Projection Explanation: Oconee 3

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 732.0 -29.55 days
Reactor Type (NSSS) B&W LLP +14.87 days
State SC +5.93 days
Age at Outage (years) 53.4 -5.4 days
Prior Cycle Length (months) 24.1 +4.33 days
Containment Type PWR-DRYAMB -3.96 days
Licensed Capacity (MWt) 2610.0 +2.12 days
Balancing Authority DUK +1.94 days
Years to License Expiration 26.2 -1.65 days
max_cycle_deviation_pct 0.3 -1.08 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?