Projection Explanation: Oconee 3

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 732.0 -38.37 days
Reactor Type (NSSS) B&W LLP +16.87 days
State SC +5.52 days
Age at Outage (years) 53.4 -5.51 days
Balancing Authority DUK +5.11 days
Licensed Capacity (MWt) 2610.0 +4.4 days
Containment Type PWR-DRYAMB -3.96 days
Outage Number (experience) 16.0 -2.1 days
NRC Region 2.0 +1.43 days
Prior Cycle Length (months) 24.1 +1.13 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?