Projection Explanation: Palo Verde 2

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 531.0 +28.11 days
Containment Type PWR-DRYAMB -8.96 days
State AZ -5.75 days
Reactor Type (NSSS) COMB CE80 +2.21 days
NRC Region 4.0 -1.82 days
Outage Number (experience) 19.0 -1.57 days
unit_modal_month 10.0 -1.09 days
unit_pct_in_winter 0.0 -0.59 days
Previous Outage Duration 37.0 +0.55 days
Month 9.0 +0.5 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?