Projection Explanation: Prairie Island 1
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Years to License Expiration |
6.9 |
+16.24 days |
| Net Capacity (MWe) |
521.0 |
+9.62 days |
| Age at Outage (years) |
52.8 |
-6.39 days |
| Cycle Length (days) |
707.0 |
-5.57 days |
| Licensed Capacity (MWt) |
1677.0 |
+4.87 days |
| Forced Outage Days in Cycle |
98.0 |
+3.83 days |
| Outage Number (experience) |
15.0 |
-3.64 days |
| Prior Cycle Length (months) |
23.3 |
+3.11 days |
| Containment Type |
PWR-DRYAMB |
-2.81 days |
| State |
MN |
+2.54 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?