Prediction Explanation: Prairie Island 2

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 735.0 -33.41 days
Prior Cycle Length (months) 24.2 +28.64 days
Net Capacity (MWe) 519.0 +17.35 days
3-Outage Rolling Avg Duration 68.7 -12.06 days
Previous Outage Duration 146.0 -10.69 days
Licensed Capacity (MWt) 1677.0 +2.36 days
unit_n_prior_refuels 12.0 -2.33 days
Day of Week 6.0 +1.95 days
Fleet Outages This Year N/A -1.86 days
Outages Since Major Maintenance 1.0 -1.8 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?