Projection Explanation: Salem 1
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
539.0 |
+22.56 days |
| Containment Type |
PWR-DRYAMB |
-9.08 days |
| Reactor Type (NSSS) |
WEST 4LP |
-5.45 days |
| Licensed Capacity (MWt) |
3459.0 |
-1.22 days |
| State |
NJ |
+1.13 days |
| Units at Site |
2.0 |
-1.13 days |
| Avg Outages Between Major Maint. |
3.7 |
-1.03 days |
| Net Capacity (MWe) |
1153.0 |
-0.98 days |
| unit_modal_month |
10.0 |
-0.88 days |
| Outage Number (experience) |
19.0 |
-0.74 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?