Projection Explanation: Summer

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 525.0 +37.39 days
Years to License Expiration 34.9 +13.86 days
Containment Type PWR-DRYAMB -8.28 days
Reactor Type (NSSS) WEST 3LP -6.25 days
State SC +3.31 days
Avg Outages Between Major Maint. 2.2 -2.35 days
unit_pct_in_predicted_month 0.0 -2.08 days
Units at Site 1.0 +1.5 days
Net Capacity (MWe) 977.0 -1.38 days
Outage Number (experience) 19.0 -1.3 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?