Lianjiang
Reactor Data
Reactor Units
Every power reactor at this site as listed in the IAEA Power Reactor Information System (PRIS): reactor type and model, net electrical capacity, grid connection and commercial operation dates, and current status.
2 units: 2 under construction.
| Unit | Type | Model | Net MWe | Construction | Grid | Commercial Op | Shutdown | Status |
|---|---|---|---|---|---|---|---|---|
| Lianjiang 1 | PWR | CAP1000 | 1,224 | 2023-09-27 | Under Construction | |||
| Lianjiang 2 | PWR | CAP1000 | 1,224 | 2024-04-26 | Under Construction |
Capacity, milestones and suppliers
| Unit | Design MWe | Gross MWe | Thermal MWt | First Criticality | Reactor Supplier | Turbine Supplier | Notes |
|---|---|---|---|---|---|---|---|
| Lianjiang 1 | 1,224 | 1,224 | 3,400 | Shanghai Nuclear Power Equipment Manufacturing Co. LTD | Dongfang Electric Corporation | ||
| Lianjiang 2 | 1,224 | 1,224 | 3,400 | China First Heavy Industries | Dongfang Electric Corporation |
Operator: Zhanjiang Nuclear Power Company, Ltd.
Owner: China Power Investment Group
Source: IAEA Power Reactor Information System (PRIS), as of 2026-10-19.
Working Here
Per Diem Rates FY 2026
Per diem covers lodging and meals & incidental expenses (M&IE) for government and contractor travel near this facility. Rates are from the U.S. State Department foreign per diem tables for FY 2026.
$170
Lodging/Night
$98
M&IE/Day
$268
Total/Day
China: rate for locations the State Department does not list separately
U.S. Department of State foreign per diem, for U.S. government and contractor travel.
Facility Map
Interactive satellite map showing the facility's geographic location. Marker color indicates current status: green for online, red for offline, orange for reduced power. Click the header to open in Google Maps satellite view.
21.5542, 109.807
Location & Contact
Physical address, phone number, and website for this facility. Use the directions link to get driving directions via Google Maps.
Plant Facts
About This Site
Written by NukeWorker from public records: facts that do not change. Operator, status and capacity come from the live data elsewhere on this page. Sources: World Nuclear News: Construction of first unit at Lianjiang under way.
Lianjiang is a nuclear power plant site in Guangdong Province, China.
Read more
China's State Council approved the first two units, CAP1000 pressurized water reactors (the Chinese version of the Westinghouse AP1000), in September 2022, and excavation began that month. Pouring of the first concrete for the Unit 1 nuclear island foundation, which took 53 hours of continuous work, was completed on 29 September 2023.