Millstone 1

DECON

Dominion Energy·Waterford, CT·BWR·641 MWe

Technical specifications, NRC licensing data, photos, nearby jobs, satellite map, contact information, and per diem rates for Millstone 1.

DECON

Permanently shut down on 1998-07-01.

Reactor Data

Reactor Units

?
Every power reactor at this site as listed in the IAEA Power Reactor Information System (PRIS): reactor type and model, net electrical capacity, grid connection and commercial operation dates, and current status.
1 unit: 1 permanent shutdown.
Unit Type Model Net MWe Construction Grid Commercial Op Shutdown Status
Millstone 1 BWR 641 1966-05-01 1970-11-29 1971-03-01 1998-07-01 Permanent Shutdown
Capacity, milestones and suppliers
Unit Design MWe Gross MWe Thermal MWt First Criticality Reactor Supplier Turbine Supplier Notes
Millstone 1 660 684 2,011 1970-10-26 GENERAL ELECTRIC CO.
Lifetime performance, through 2025
Unit Electricity Supplied Load Factor Energy Availability Operating Factor
Millstone 1 101.4 TWh 65.0% 70.5% 69.0%
Operator: Dominion Energy
Source: IAEA Power Reactor Information System (PRIS), as of 2026-10-19.

Working Here

Per Diem Rates FY 2027

?
Per diem covers lodging and meals & incidental expenses (M&IE) for government and contractor travel near this facility. Rates are from GSA for FY 2027.
$149
Lodging/Night
$86
M&IE/Day
$235
Total/Day
New London / Groton, New London County, CT

Unemployment Benefits CT

?
Maximum state unemployment insurance benefits for CT. Actual benefits depend on your earnings history and may be lower than the maximum. Data as of Jan 2026.
$826
Max Weekly
26
Max Weeks
$21,476
Max Total

Location & Contact

?
Physical address, phone number, and website for this facility. Use the directions link to get driving directions via Google Maps.
Address:
Rope Ferry Road
Waterford, CT 06385, USA
Get Directions
Phone: (860) 444-5797

Plant Facts

About This Site

?
Written by NukeWorker from public records: facts that do not change. Operator, status and capacity come from the live data elsewhere on this page. Sources: Wikipedia: Millstone Nuclear Power Station.

Millstone Nuclear Power Station is at Waterford, in New London County, Connecticut, on Long Island Sound, on the site of a former quarry. It was built with three units.

Read more

Construction began on Unit 1 (General Electric boiling water reactor) in May 1966, Unit 2 (Combustion Engineering pressurized water reactor) in November 1969, and Unit 3 (Westinghouse pressurized water reactor) in August 1974. They connected to the grid in 1970, 1975 and 1986. A leaking valve in February 1996 led to the shutdown of all the reactors for repairs. Unit 3 restarted in July 1998 and Unit 2 in May 1999. Unit 1 was permanently shut down in July 1998, because the cost of fixing its safety issues was too high.

Ownership & Construction

?
The utility or company that owns and operates the facility, the architect-engineer responsible for plant design, and the primary construction contractor. Click names to view all facilities by that entity on the map.
Owner/Operator: Dominion Energy
Architect Engineer: EBSO
Constructor: EBSO
D Dominion Energy, Inc. NYSE
$65.32 ▲ +2.99 (+4.79%)
Previous Close 62.33
Day's Range 62.73 – 65.43
52-Week Range 55.85 – 72.99
Volume 3,822,492
Delayed quote as of Oct 22, 2026 3:38 PM ET. Source: Yahoo Finance. Full quote on Yahoo Finance
Dominion Energy and NextEra Energy (NEE) announced a merger on 2026-05-18. It is still subject to regulatory and shareholder approval, so Dominion remains the owner of record here until the deal closes.

Technical Specs

?
Reactor design specifications including type (PWR/BWR), containment design, nuclear steam supply system manufacturer, thermal and electrical power ratings, and current operational status.
Reactor Type: BWR
Containment: BWR-MARK1
NSS Supplier: GE 3
Thermal Power: 2011 MWt
Net Capacity: 641 MWe
Status: DECON

Licensing

?
NRC licensing history including docket number, license type and number, construction permit date, operating license issuance, commercial operation date, license renewal, and expiration date.
Docket #: 05000245
License #: DPR-21
License Type: OL-FP
Const. Permit: 1966-05-19
Operating Lic: 1986-10-31
Commercial Op: 1971-03-01
License Exp: 2010-10-06