Obrigheim

Technical specifications, photos, nearby jobs, and satellite map for Obrigheim.

Reactor Data

Reactor Units

?
Every power reactor at this site as listed in the IAEA Power Reactor Information System (PRIS): reactor type and model, net electrical capacity, grid connection and commercial operation dates, and current status.
1 unit: 1 permanent shutdown.
Unit Type Model Net MWe Construction Grid Commercial Op Shutdown Status
Obrigheim PWR PWR 340 1965-03-15 1968-10-29 1969-03-31 2005-05-11 Permanent Shutdown
Capacity, milestones and suppliers
Unit Design MWe Gross MWe Thermal MWt First Criticality Reactor Supplier Turbine Supplier Notes
Obrigheim 283 357 1,050 1968-09-22 SIEMENS AG, KRAFTWERK UNION AG Siemens AG, Power Generation Decommissioning from 2008-08-28
Lifetime performance, through 2025
Unit Electricity Supplied Load Factor Energy Availability Operating Factor
Obrigheim 86.8 TWh 81.1% 82.4% 83.6%
Operator: EnBW Kraftwerke AG
Owner: KERNKRAFTWERK OBRIGHEIM GMBH
Source: IAEA Power Reactor Information System (PRIS), as of 2026-10-19.

Fuel Cycle Facilities

?
Fuel cycle plants at this site, as listed in the IAEA Nuclear Fuel Cycle Facilities Database: what each plant does, its scale and design capacity, the years it operated, its current status and who operates it.
2 facilities: 1 decommissioning, 1 others.
Facility Type Scale Design Capacity Operated Status Operator
Obrigheim NPP On-Site Interim Storage Facility (temporary) AFR Wet Spent Fuel Storage (Pool) Commercial 286 t HM 1999–2017 Decommissioning EnBW Kernkraft GmbH
Obrigheim NPP On-Site Storage Facility AFR Dry Spent Fuel Storage Commercial 100 t HM Others EnBW Kernkraft GmbH
Source: IAEA Nuclear Fuel Cycle Facilities Database (NFCFDB), as of 2026-10-13.

Working Here

Per Diem Rates FY 2026

?
Per diem covers lodging and meals & incidental expenses (M&IE) for government and contractor travel near this facility. Rates are from the U.S. State Department foreign per diem tables for FY 2026.
$237
Lodging/Night
$140
M&IE/Day
$377
Total/Day
Germany: rate for locations the State Department does not list separately
U.S. Department of State foreign per diem, for U.S. government and contractor travel.

Location & Contact

?
Physical address, phone number, and website for this facility. Use the directions link to get driving directions via Google Maps.
Address:
Obrigheim, Baden-Württemberg, Germany
Get Directions

Plant Facts

About This Site

?
Written by NukeWorker from public records: facts that do not change. Operator, status and capacity come from the live data elsewhere on this page. Sources: Wikipedia: Obrigheim Nuclear Power Plant.

Obrigheim is a nuclear power plant at Obrigheim in the Neckar-Odenwald district of Baden-Württemberg, Germany, on the banks of the Neckar River.

Read more

Construction began in 1965. The plant had a single pressurized water reactor supplied by Siemens-Schuckert. It was connected to the grid on 29 October 1968 and entered commercial operation on 31 March 1969. The reactor was permanently shut down on 11 May 2005. Decommissioning began that year, and the fuel was removed from the reactor by 2007.