Pickering

Pickering, ON·CANDU

Community ratings, technical specifications, photos, nearby jobs, satellite map, and per diem rates for Pickering.

Reactor Data

Reactor Units

?
Every power reactor at this site as listed in the IAEA Power Reactor Information System (PRIS): reactor type and model, net electrical capacity, grid connection and commercial operation dates, and current status.
8 units: 4 operational, 4 permanent shutdown. Net capacity in service: 2,064 MWe.
Unit Type Model Net MWe Construction Grid Commercial Op Shutdown Status
Pickering 1 PHWR CANDU 500A 515 1966-06-01 1971-04-04 1971-07-29 2024-10-01 Permanent Shutdown
Pickering 2 PHWR CANDU 500A 515 1966-09-01 1971-10-06 1971-12-30 2007-05-28 Permanent Shutdown
Pickering 3 PHWR CANDU 500A 515 1967-12-01 1972-05-03 1972-06-01 2008-10-31 Permanent Shutdown
Pickering 4 PHWR CANDU 500A 515 1968-05-01 1973-05-21 1973-06-17 2024-12-31 Permanent Shutdown
Pickering 5 PHWR CANDU 500B 516 1974-11-01 1982-12-19 1983-05-10 Operational
Pickering 6 PHWR CANDU 500B 516 1975-10-01 1983-11-08 1984-02-01 Operational
Pickering 7 PHWR CANDU 500B 516 1976-03-01 1984-11-17 1985-01-01 Operational
Pickering 8 PHWR CANDU 500B 516 1976-09-01 1986-01-21 1986-02-28 Operational
Capacity, milestones and suppliers
Unit Design MWe Gross MWe Thermal MWt First Criticality Reactor Supplier Turbine Supplier Notes
Pickering 1 508 542 1,744 1971-02-25 ONTARIO HYDRO / ATOMIC ENERGY OF CANADA, LTD. NEI PARSONS Suspended 1997-12-31; Restarted 2005-09-26
Pickering 2 508 542 1,744 1971-09-15 ONTARIO HYDRO / ATOMIC ENERGY OF CANADA, LTD. NEI PARSONS Suspended 1997-12-31; Restarted 2007-05-28
Pickering 3 508 542 1,744 1972-04-24 ONTARIO HYDRO / ATOMIC ENERGY OF CANADA, LTD. NEI PARSONS Suspended 1997-12-29; Restarted 2008-10-31
Pickering 4 508 542 1,744 1973-05-16 ONTARIO HYDRO / ATOMIC ENERGY OF CANADA, LTD. NEI PARSONS Suspended 1998-01-02; Restarted 2003-09-21
Pickering 5 516 540 1,744 1982-10-23 ONTARIO HYDRO / ATOMIC ENERGY OF CANADA, LTD. NEI PARSONS
Pickering 6 516 540 1,744 1983-10-15 ONTARIO HYDRO / ATOMIC ENERGY OF CANADA, LTD. ONTARIO HYDRO / ATOMIC ENERGY OF CANADA, LTD.
Pickering 7 516 540 1,744 1984-10-22 ONTARIO HYDRO / ATOMIC ENERGY OF CANADA, LTD. NEI PARSONS
Pickering 8 516 540 1,744 1985-12-17 ONTARIO HYDRO / ATOMIC ENERGY OF CANADA, LTD. NEI PARSONS
Lifetime performance, through 2025
Unit Electricity Supplied Load Factor Energy Availability Operating Factor
Pickering 1 138.2 TWh 67.0% 69.0% 70.3%
Pickering 2 71.4 TWh 60.3% 62.4% 62.5%
Pickering 3 80.0 TWh 68.9% 70.6% 70.7%
Pickering 4 143.3 TWh 69.1% 69.2% 72.3%
Pickering 5 143.8 TWh 74.3% 74.5% 78.0%
Pickering 6 150.1 TWh 78.8% 78.9% 81.5%
Pickering 7 146.1 TWh 78.6% 78.6% 81.1%
Pickering 8 137.6 TWh 76.3% 76.4% 79.5%
Operator: Ontario Power Generation
Owner: Ontario Power Generation
Source: IAEA Power Reactor Information System (PRIS), as of 2026-10-19.

Fuel Cycle Facilities

?
Fuel cycle plants at this site, as listed in the IAEA Nuclear Fuel Cycle Facilities Database: what each plant does, its scale and design capacity, the years it operated, its current status and who operates it.
1 facility: 1 in operation.
Facility Type Scale Design Capacity Operated Status Operator
Pickering Waste Management Facility AFR Dry Spent Fuel Storage Commercial 1758 Cask-Bund. 1996– In Operation Ontario Power Generation
Source: IAEA Nuclear Fuel Cycle Facilities Database (NFCFDB), as of 2026-10-13.

Working Here

Per Diem Rates FY 2026

?
Per diem covers lodging and meals & incidental expenses (M&IE) for government and contractor travel near this facility. Rates are from the U.S. State Department foreign per diem tables for FY 2026.
$167
Lodging/Night
$120
M&IE/Day
$287
Total/Day
Canada: rate for locations the State Department does not list separately
U.S. Department of State foreign per diem, for U.S. government and contractor travel.

Location & Contact

?
Physical address, phone number, and website for this facility. Use the directions link to get driving directions via Google Maps.
Address:
Pickering, ON L1V2R5, Canada
Get Directions

Plant Facts

About This Site

?
Written by NukeWorker from public records: facts that do not change. Operator, status and capacity come from the live data elsewhere on this page. Sources: Wikipedia: Pickering Nuclear Generating Station.

Pickering is a nuclear power station on the north shore of Lake Ontario at Pickering, in Durham Region, Ontario.

Read more

Ontario Hydro built it in stages between 1965 and 1986, with eight CANDU reactors supplied by AECL: Pickering A and Pickering B. Construction of Unit 1 began on 1 June 1966 and Unit 8 on 1 September 1976. On 1 August 1983 a pressure tube in Unit 2 split, and the reactor was shut down safely. The four Pickering A units were laid up on 31 December 1997. Unit 4 restarted in September 2003 and Unit 1 in November 2005. Units 2 and 3 were permanently shut down in 2007 and 2008, Unit 1 on 1 October 2024 and Unit 4 on 31 December 2024.

Technical Specs

?
Reactor design specifications including type (PWR/BWR), containment design, nuclear steam supply system manufacturer, thermal and electrical power ratings, and current operational status.
Reactor Type: CANDU