Projection Explanation: Byron 2

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Containment Type PWR-DRYAMB -12.05 days
Cycle Length (days) 553.0 +11.16 days
Reactor Type (NSSS) WEST 4LP -7.08 days
Units at Site 2.0 -2 days
State IL -1.53 days
Net Capacity (MWe) 1136.0 -1.07 days
Outage Number (experience) 18.0 -0.95 days
Licensed Capacity (MWt) 3645.0 -0.71 days
Avg Outages Between Major Maint. N/A +0.68 days
Age at Outage (years) 39.2 +0.59 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?