Projection Explanation: Calvert Cliffs 2
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
735.0 |
-27.31 days |
| Reactor Type (NSSS) |
COMB CE |
+7.4 days |
| Containment Type |
PWR-DRYAMB |
-4.34 days |
| State |
MD |
+2.75 days |
| Net Capacity (MWe) |
861.0 |
+2.19 days |
| unit_pct_in_winter |
0.8 |
+2.13 days |
| unit_pct_in_spring_fall |
0.2 |
+1.98 days |
| Units at Site |
2.0 |
-1.67 days |
| unit_pct_in_predicted_month |
0.8 |
+1.64 days |
| NRC Region |
1.0 |
+1.58 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?