Projection Explanation: Catawba 1

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Containment Type PWR-ICECND -11.33 days
Reactor Type (NSSS) WEST 4LP -6.1 days
Years to License Expiration 16.1 -3.41 days
State SC +2.91 days
Prior Cycle Length (months) 18.6 -2.8 days
Cycle Length (days) 564.0 +2.4 days
Balancing Authority DUK +2.35 days
Units at Site 2.0 -1.82 days
Net Capacity (MWe) 1160.0 -1.68 days
Licensed Capacity (MWt) 3469.0 -0.93 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?