Projection Explanation: Dresden 2

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 728.0 -40.55 days
Containment Type BWR-MARK 1 +28.23 days
Reactor Type (NSSS) GE 3 +5.66 days
Age at Outage (years) 57.4 -4.78 days
Units at Site 2.0 -1.84 days
unit_pct_in_predicted_month 0.8 +1.62 days
Prior Cycle Length (months) 23.9 +1.4 days
State IL -1.31 days
Outage Number (experience) 14.0 -0.74 days
unit_modal_month 10.0 -0.69 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?