Prediction Explanation: Dresden 3
Feature importance and per-unit prediction explanations for the model.
Per-Unit Prediction Explanation
Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Prior Cycle Length (months) |
23.9 |
+29.25 days |
| Cycle Length (days) |
728.0 |
-27.79 days |
| Containment Type |
BWR-MARK 1 |
+1.44 days |
| 3-Outage Rolling Avg Duration |
15.3 |
+1.05 days |
| unit_pct_in_spring_fall |
0.9 |
-0.66 days |
| Fleet Density |
N/A |
-0.65 days |
| Fleet Outages This Year |
8.0 |
+0.62 days |
| Reactor Type (NSSS) |
GE 3 |
+0.6 days |
| unit_pct_in_predicted_month |
0.3 |
+0.44 days |
| Day of Week |
1.0 |
-0.4 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?