Projection Explanation: Farley 1
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
539.0 |
+21.08 days |
| Containment Type |
PWR-DRYAMB |
-9.06 days |
| Reactor Type (NSSS) |
WEST 3LP |
-3.05 days |
| State |
AL |
-2.72 days |
| Licensed Capacity (MWt) |
2775.0 |
-1.49 days |
| Outage Number (experience) |
18.0 |
-0.94 days |
| Units at Site |
2.0 |
-0.92 days |
| Net Capacity (MWe) |
895.0 |
-0.84 days |
| Previous Outage Duration |
31.0 |
+0.6 days |
| Years to License Expiration |
10.2 |
-0.46 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?