Projection Explanation: Ginna
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Containment Type |
PWR-DRYAMB |
-11.93 days |
| Cycle Length (days) |
553.0 |
+11.14 days |
| Units at Site |
1.0 |
+7.39 days |
| Age at Outage (years) |
57.3 |
-6.34 days |
| Reactor Type (NSSS) |
WEST 2LP |
-5.97 days |
| Balancing Authority |
NYIS |
-3.92 days |
| Avg Outages Between Major Maint. |
N/A |
+3.06 days |
| unit_pct_in_spring_fall |
1.0 |
-2.18 days |
| Licensed Capacity (MWt) |
1775.0 |
+2.12 days |
| Net Capacity (MWe) |
581.0 |
-2.03 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?
Page created in 0.005 seconds with 0 queries.