Projection Explanation: Hatch 1
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Containment Type |
BWR-MARK 1 |
+30.19 days |
| Cycle Length (days) |
713.0 |
-25.9 days |
| Month |
1.0 |
-9.71 days |
| Units at Site |
2.0 |
-2.82 days |
| Reactor Type (NSSS) |
GE 4 |
+2.71 days |
| unit_pct_in_winter |
0.8 |
+2.07 days |
| unit_pct_in_predicted_month |
0.1 |
-2.02 days |
| Prior Cycle Length (months) |
23.4 |
+1.39 days |
| Outage Number (experience) |
15.0 |
-1.18 days |
| Fleet Density |
0.2 |
+0.87 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?