Projection Explanation: Hatch 1

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 713.0 -32.78 days
Containment Type BWR-MARK 1 +30.88 days
Month 1.0 -12.4 days
Reactor Type (NSSS) GE 4 +7.45 days
Units at Site 2.0 -2.37 days
unit_pct_in_winter 0.8 +2.34 days
unit_pct_in_spring_fall 0.2 +1.71 days
Prior Cycle Length (months) 23.4 +1.51 days
Outage Number (experience) 15.0 -1.09 days
Fleet Outages This Year 3.0 -0.9 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?