Projection Explanation: Monticello

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 735.0 -48.86 days
Containment Type BWR-MARK 1 +25.37 days
Age at Outage (years) 55.8 -6.19 days
Avg Outages Between Major Maint. 2.3 -5.74 days
Reactor Type (NSSS) GE 3 +4.98 days
Units at Site 1.0 +3.8 days
State MN +3.41 days
Owner Xcel Energy +2.46 days
Balancing Authority MISO -1.84 days
unit_pct_in_predicted_month 0.5 +1.77 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?