Projection Explanation: Monticello
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
735.0 |
-48.86 days |
| Containment Type |
BWR-MARK 1 |
+25.37 days |
| Age at Outage (years) |
55.8 |
-6.19 days |
| Avg Outages Between Major Maint. |
2.3 |
-5.74 days |
| Reactor Type (NSSS) |
GE 3 |
+4.98 days |
| Units at Site |
1.0 |
+3.8 days |
| State |
MN |
+3.41 days |
| Owner |
Xcel Energy |
+2.46 days |
| Balancing Authority |
MISO |
-1.84 days |
| unit_pct_in_predicted_month |
0.5 |
+1.77 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?