Projection Explanation: Oconee 1
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
724.0 |
-33.38 days |
| Reactor Type (NSSS) |
B&W LLP |
+18.27 days |
| Balancing Authority |
DUK |
+7.31 days |
| Licensed Capacity (MWt) |
2610.0 |
+6.48 days |
| State |
SC |
+5.68 days |
| Age at Outage (years) |
53.3 |
-5.58 days |
| Containment Type |
PWR-DRYAMB |
-4.02 days |
| Net Capacity (MWe) |
862.0 |
+3.33 days |
| Outage Number (experience) |
16.0 |
-2.1 days |
| NRC Region |
2.0 |
+1.26 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?