Projection Explanation: Point Beach 1
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Containment Type |
PWR-DRYAMB |
-13.28 days |
| Age at Outage (years) |
57.3 |
-8.07 days |
| Reactor Type (NSSS) |
WEST 2LP |
-4.05 days |
| Licensed Capacity (MWt) |
1800.0 |
+3.67 days |
| Cycle Length (days) |
567.0 |
+3.46 days |
| Balancing Authority |
MISO |
-2.98 days |
| Units at Site |
2.0 |
-1.87 days |
| Outage Number (experience) |
19.0 |
-1.82 days |
| State |
WI |
+1.54 days |
| unit_modal_month |
10.0 |
-1.42 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?