Projection Explanation: Surry 1

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Containment Type PWR-DRYSUB -12.03 days
Cycle Length (days) 553.0 +10.58 days
3-Outage Rolling Avg Duration 60.3 +6.6 days
Age at Outage (years) 54.3 -6.51 days
Reactor Type (NSSS) WEST 3LP -6.44 days
State VA +5.89 days
Balancing Authority PJM -3.68 days
Licensed Capacity (MWt) 2587.0 +1.81 days
Outage Number (experience) 18.0 -1.74 days
NRC Region 2.0 +1.42 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?