Projection Explanation: Surry 2
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
532.0 |
+23.92 days |
| Containment Type |
PWR-DRYSUB |
-8.1 days |
| Age at Outage (years) |
54.4 |
-6.82 days |
| Reactor Type (NSSS) |
WEST 3LP |
-5.92 days |
| Balancing Authority |
PJM |
-3.5 days |
| State |
VA |
+3.45 days |
| Outage Number (experience) |
19.0 |
-2.14 days |
| Licensed Capacity (MWt) |
2587.0 |
+1.91 days |
| unit_pct_in_winter |
0.0 |
-1.11 days |
| Net Capacity (MWe) |
838.0 |
-1.07 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?