Projection Explanation: Watts Bar 1
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Forced Outage Days in Cycle |
108.0 |
+30.78 days |
| Cycle Length (days) |
532.0 |
+15.01 days |
| Containment Type |
PWR-ICECND |
-6.54 days |
| Years to License Expiration |
8.1 |
+4.9 days |
| Age at Outage (years) |
31.4 |
+4.01 days |
| Reactor Type (NSSS) |
WEST 4LP |
-3.66 days |
| State |
TN |
+2.96 days |
| Outage Number (experience) |
19.0 |
-2.24 days |
| Prior Cycle Length (months) |
17.5 |
-1.77 days |
| Fleet Outages This Year |
2.0 |
+1.64 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?