Composite Operational Excellence Score (0-100) — average percentile rank across 7 dimensions in three sub-scores: Reliability (capacity factor, forced outage days, B2B avg streak), Efficiency (fuel utilization, refuel duration), and Discipline (startup duration, scram count). 5-year window. Higher = more operationally excellent. Click to see the full breakdown.
Excellence
ranked of 93
Subscribers
?
Current reactor power level from the most recent NRC daily report.
0%
Power
OFFLINE (4 Days)
?
Days of continuous operation since the last outage ended. Ranked against all operating units.
--
Current Run
days
#93 of 95
Bottom Quartile
?
Longest recorded period of continuous operation between outages.
549
Record Run
days
#64 of 95
Mid Quartile
?
Breaker-to-Breaker runs — continuous operation exceeding the cycle-adjusted threshold (461 days for this 18-month cycle unit) with no trips to 0% power.
4
B2B Runs
#58 of 86
Mid Quartile
?
Lifetime capacity factor: average power level across all recorded days (100% = always at full power). Ranked against all NRC-tracked units.
88.5%
Capacity Factor
#70 of 95
Mid Quartile
?
Net electricity actually generated over the most recent 12 months reported by the U.S. Energy Information Administration (Form EIA-923), summed across every unit at this plant. These are authoritative actuals, not an estimate.
17.88 TWh
Net Generation
EIA-923 · 12 mo to 2026-07 · plant total
?
Community rating score (Bayesian-adjusted). Based on 49 votes. Ranked against all rated facilities.
59.7
Rating
49 votes
#15 of 97
Top Quartile
?
Total NRC-reported scram events (emergency reactor shutdowns). Ranked fleet-wide — fewer scrams = better rank.
6
Scrams
#33 of 94
Mid Quartile
?
Years since commercial operation began. License remaining: 14.9 years.
44.3
Operating Age
years
14.9 yrs remaining
Reactor Status Timeline
Refueling Outage · Day 4 NRC data, Mon to Fri ? Actual daily reactor status from NRC reports (Mon to Fri) and the current state. What is coming -- the utility's published Scheduled outage and NukeWorker's model Projection -- is part of a subscription. Colored by status. How far ahead you can see depends on your plan.OnlineCoastdownPower AscensionRefueling OutageForced Outage
Operational Excellence Score Subscribers
Sequoyah 2 is rated 0 to 100 on how well it actually runs, scored against every other operating reactor in the US fleet from its own operating record. Subscribers see the score, the three sub-scores behind it, and each of the seven measured inputs.
- This unit's composite score and fleet rank
- Reliability, Efficiency and Discipline sub-scores
- All seven measured inputs, with fleet percentiles
- Rank against comparable units, not just the fleet
- Three-year, five-year and lifetime windows
- Five-year trend, and every other operating US reactor
Included with every outage subscription and with NukeWorker Gold membership. Trading the outage rather than working it? The same record, cut by power market, is on NukeGryd.
Capacity Factor (365-Day)
0%
Current
96.8%
365-Day Avg
#13
of 94 plants
Min: 0%
Max: 100%
12 days <80%
Breaker-to-Breaker Runs 4 runs
Breaker-to-breaker runs measure continuous operation between refueling outages using a cycle-adjusted threshold (90% of cycle length minus RFO duration). An active streak means the unit has been running continuously since the last refueling with no trips to 0% power.
Sequoyah 2 has logged 4 breaker-to-breaker runs, continuous stretches from one refueling to the next with no trip to zero power. Its longest ran 516 days, and its runs average 510 days.
516
Best Run (days)
U2R10 (2000-11-15) → U2R11 (2002-04-15)
510
Avg Run (days)
★ Double breaker-to-breaker
U2R23 → U2R24 → U2R25
All Runs
| 2021-11-08 | 2023-03-18 | 495 days | U2R24 → U2R25 |
| 2020-05-05 | 2021-10-02 | 515 days | U2R23 → U2R24 |
| 2017-06-06 | 2018-11-03 | 515 days | U2R21 → U2R22 |
| 2000-11-15 | 2002-04-15 | 516 days | U2R10 → U2R11 |
Scram History 6 events since 2011
Automatic and manual reactor scram (emergency shutdown) events reported to the NRC since 2011. Includes event dates, trip type, and average recovery time. Click the title to view the full fleet scram dashboard.
Sequoyah 2 has recorded 6 reactor scrams, or emergency shutdowns, since 2011 (3 automatic, 3 manual). On average the unit was back to full power about 6 days after each trip.
Outage Duration Trend
?Scheduled refueling outage durations over time. Green bars are below average, yellow near average, red above. Dashed line shows the plant's historical average. Shorter outages mean better execution.
Sequoyah 2 has completed 18 scheduled refueling outages on record, averaging 32 days each. The most recent, in Oct 2026, ran 4 days.
Power History (12-Month)
?Daily power output as a percentage of rated capacity over the past 365 days. Green segments indicate full power (90%+), yellow shows reduced output, and red indicates significant power reductions or shutdowns.
Over the past 12 months Sequoyah 2 has run at an average of 96.8% of rated power. On the chart, green stretches are full-power running and dips toward zero mark reduced output or outages.
Outage Days by Year
?Total days spent in outage each year, split by scheduled refueling (blue) and forced/unplanned (red). Lower totals indicate better reliability and outage execution. Hover for details.
Across its recorded history, Sequoyah 2 has spent 570 days in scheduled refueling outages and 138 days in forced or unplanned outages. Taller bars mark the years with the most downtime.
Facility Statistics
Key performance and lifecycle metrics calculated from NRC operational data. Includes operating age, construction timeline, capacity factor, efficiency, generation totals, and reliability records.
Sequoyah 2 has operated for about 44.3 years and averaged a 88.5% lifetime capacity factor, generating roughly 245.0 TWh of electricity. Its longest unbroken run reached 549 days.
Lifecycle & Tenure
Operating Age: 44.3 Yrs
Build Time: 12 Yrs
Lic. Remaining: 14.9 Yrs
Production & Power
Lifetime CF: 88.5%
Efficiency: 32.6%
Generated: 245.0 TWh
Reliability & Outages
Record Run: 549 Days
Refuelings: 19
Avg Startup: 6.8 Days
NukeWorker Member Ratings 49 votes
Community ratings from NukeWorker members. Vote to share your experience working at this facility. Score uses a Bayesian average that accounts for vote count — facilities with few votes are pulled toward the fleet average, so rankings reflect confidence, not just raw percentages.
Above Average
25 (51%)
Average
14 (28%)
Below Average
10 (20%)
Facility Map
Interactive satellite map showing the facility's geographic location. Marker color indicates current status: green for online, red for offline, orange for reduced power. Click the header to open in Google Maps satellite view.
35.2259, -85.09
Location & Contact
Physical address, phone number, and website for this facility. Use the directions link to get driving directions via Google Maps.
Phone:
(423) 843-6000
Website:
http://www.tva.gov/
Per Diem Rates FY 2027
Per diem covers lodging and meals & incidental expenses (M&IE) for government and contractor travel near this facility. Rates are from GSA for FY 2027.
$113
Lodging/Night
$68
M&IE/Day
$181
Total/Day
Standard Rate, TN
Unemployment Benefits TN
Maximum state unemployment insurance benefits for TN. Actual benefits depend on your earnings history and may be lower than the maximum. Data as of Jan 2026.
$275
Max Weekly
26
Max Weeks
$7,150
Max Total
7-day waiting period before benefits begin
Jobs in TN 74 active
Active nuclear industry job listings in TN from the NukeWorker job board. Click a job title for full details, or click the header to search all jobs in this state.
Photos
Photos of this facility from the NukeWorker photo gallery. Click the header or any photo to browse the full album.
Ownership & Construction
The utility or company that owns and operates the facility, the architect-engineer responsible for plant design, and the primary construction contractor. Click names to view all facilities by that entity on the map.
Publicly Traded
No — Federal corporation with no common equity. Its listed TVC/TVE securities are power bonds, not stock.
Technical Specs
Reactor design specifications including type (PWR/BWR), containment design, nuclear steam supply system manufacturer, thermal and electrical power ratings, and current operational status.
Reactor Type:
PWR
Containment:
PWR-ICECND
NSS Supplier:
WEST 4LP
Thermal Power:
3455 MWt
Net Capacity:
1126 MWe
Efficiency:
32.6%
Status:
Operating
Licensing
NRC licensing history including docket number, license type and number, construction permit date, operating license issuance, commercial operation date, license renewal, and expiration date.
Docket #:
05000328
License #:
DPR-79
License Type:
OL-FP
Const. Permit:
1970-05-27
Operating Lic:
1981-09-15
Commercial Op:
1982-06-01
License Renewed:
2015-09-24
License Exp:
2041-09-15
Market & Region
EIA market and grid-region classifications: NERC reliability region, U.S. Census region, balancing authority responsible for grid operations, and whether the unit operates as a rate-regulated utility or a competitive merchant generator. Hover any value for the full name.
NERC Region:
SERC
— SERC Reliability Corporation
Census Region:
ESC
— East South Central
Balancing Authority:
TVA
— Tennessee Valley Authority
Market Structure:
Regulated
— Rate-regulated utility (cost-of-service pricing)