Prediction Explanation: Calvert Cliffs 1

Feature importance and per-unit prediction explanations for the model.

Per-Unit Prediction Explanation

Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Cycle Length (days) 735.0 -34.25 days
Prior Cycle Length (months) 24.2 +23.54 days
Years to License Expiration 6.5 +2.52 days
unit_pct_in_spring_fall 0.2 +2.08 days
unit_pct_in_winter 0.8 +2.07 days
Day of Week 1.0 -1.3 days
Forced Outage Days in Cycle 10.0 +0.96 days
unit_pct_in_predicted_month 0.8 +0.9 days
m6_month_dist_to_modal 0.0 -0.82 days
Containment Type PWR-DRYAMB -0.82 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?