Prediction Explanation: Saint Lucie 2
Feature importance and per-unit prediction explanations for the model.
Per-Unit Prediction Explanation
Why was this prediction made? Each bar shows how a feature pushed the prediction higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Prior Cycle Length (months) |
19.6 |
-16.21 days |
| Cycle Length (days) |
595.0 |
-10.31 days |
| unit_pct_in_predicted_month |
0.0 |
-6.1 days |
| unit_pct_in_spring_fall |
0.6 |
+2.32 days |
| Years Since Major Maintenance |
13.8 |
-1.59 days |
| Outages Since Major Maintenance |
9.0 |
-1.25 days |
| Containment Type |
PWR-DRYAMB |
-1.22 days |
| 3-Outage Rolling Avg Duration |
30.3 |
+1.11 days |
| Avg Coastdown Days (this unit) |
3.0 |
+0.98 days |
| Age at Outage (years) |
44.2 |
+0.82 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?