Projection Explanation: Sequoyah 1

Feature importance and per-unit projection explanations for the model.

Per-Unit Projection Explanation

Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.

When will the next refueling outage begin?

FeatureValueImpact (days)
Containment Type PWR-ICECND -11.08 days
Cycle Length (days) 560.0 +6.19 days
Reactor Type (NSSS) WEST 4LP -5.76 days
Years to License Expiration 13.5 -3.44 days
State TN +2.82 days
Prior Cycle Length (months) 18.4 -2.66 days
Units at Site 2.0 -1.38 days
unit_n_prior_refuels 18.0 -0.9 days
Fleet Sequence Position N/A +0.73 days
Outage Number (experience) 18.0 -0.72 days

Start Date — Global Importance

When will the next refueling outage begin?

Refueling Duration — Global Importance

How long will the next refueling outage last?

Refueling Extension — Global Importance

How many days past schedule will it run?

Forced Outage Duration — Global Importance

If a forced outage occurs now, how long will it last?