Projection Explanation: Sequoyah 2
Feature importance and per-unit projection explanations for the model.
Per-Unit Projection Explanation
Why was this projection made? Each bar shows how a feature pushed the projection higher or lower compared to the fleet average.
When will the next refueling outage begin?
| Feature | Value | Impact (days) |
| Cycle Length (days) |
501.0 |
+64.24 days |
| Containment Type |
PWR-ICECND |
-6.49 days |
| Reactor Type (NSSS) |
WEST 4LP |
-4.9 days |
| Prior Cycle Length (months) |
16.5 |
-2.17 days |
| Units at Site |
2.0 |
-2.15 days |
| cycle_interval_cv |
0.0 |
-1.97 days |
| unit_pct_in_predicted_month |
0.0 |
-1.95 days |
| Years to License Expiration |
14.0 |
-1.7 days |
| State |
TN |
+1.63 days |
| cycle_interval_std |
20.4 |
-1.56 days |
Start Date — Global Importance
When will the next refueling outage begin?
Refueling Duration — Global Importance
How long will the next refueling outage last?
Refueling Extension — Global Importance
How many days past schedule will it run?
Forced Outage Duration — Global Importance
If a forced outage occurs now, how long will it last?