• Reliability — capacity factor, forced outage days, B2B avg streak
• Efficiency — fuel utilization, refuel duration
• Discipline — startup duration, scram count
Each unit's metric is converted to a percentile across the active fleet. Sub-score = average of its components; composite = average of the three sub-scores. Use the time-window toggle below to switch between 3yr / 5yr / lifetime.
Operational
Excellence Score
McGuire 2 ranks #36 of 94 active US units on NukeWorker's Operational Excellence Score over the 5-year window. Strongest area: Fuel Utilization (66th percentile). Weakest: B2B Avg Streak (37th percentile).
Per-dimension breakdown (7 metrics)
Each dimension's percentile is computed across the active US fleet (94 units with sufficient history). Sub-score = average of its component percentiles. Composite = average of the three sub-scores. 5-year window. View full leaderboard →
Methodology
NukeWorker's Operational Excellence Score is a composite ranking that combines 7 publicly observable performance metrics into a single 0-100 number per US nuclear unit.
How it's computed: Each unit's raw value is converted to a percentile (0-100) within the 94 active US units that have at least 2 completed refueling cycles. The 7 percentiles are averaged into 3 sub-scores (Reliability, Efficiency, Discipline), and those are averaged into the final composite.
Active window — 5-year:
- Reliability — Capacity factor (5yr), forced outage days/yr (5yr), B2B avg streak (lifetime)
- Efficiency — in-cycle fuel utilization (3yr), median refuel duration (5yr)
- Discipline — robust mean startup duration, scrams/yr (5yr, annualised)
Cohort rankings: alongside the fleet rank, each unit gets ranked within its reactor type (PWR/BWR), containment design (Ice Condenser, Mark I, etc.), and cycle length (12/18/24-month). Useful for apples-to-apples comparisons.
What's excluded: subjective community ratings, confidential INPO ratings, financial metrics. We only use publicly available NRC + cycle data.
Why three windows? 5yr (default) is the industry standard. 3yr captures recent operational changes and post-pandemic recovery. Lifetime gives newer units a fair comparison and reveals long-term consistency.
Edge cases: units with fewer than 2 cycles (e.g., Vogtle 4) show "Provisional". Decommissioned units excluded.
Refresh cadence: recomputed daily. Each window cached separately.
A data-derived proxy for operational performance; not affiliated with INPO. INPO ratings are confidential and qualitative — ours is public and quantitative.
Outage Duration Trend
Cycle Length History
Startup Duration Trend
Fuel Burn Down Cycle since Apr 20, 2026
Power History
| Type ⇅ | Actual Start ⇅ | Actual End ⇅ | Duration ⇅ | Days Online ⇅ | Scheduled | Delta |
|---|---|---|---|---|---|---|
|
Scheduled
|
2026-03-22 | 2026-04-18 | 28 | 157d | 2026-03-21 | +1d |
|
Scram
# 57977
|
2025-10-10 | 2025-10-16 | 7 | 384d | - | - |
|
Scheduled
|
2024-09-01 | 2024-09-21 | 21 | 517d | 2024-09-01 | 0d |
|
Scheduled
|
2023-02-18 | 2023-04-03 | 45 | 362d | 2023-02-18 | 0d |
|
Scram
# 55748
|
2022-02-19 | 2022-02-21 | 3 | 132d | - | - |
|
Scheduled
|
2021-09-11 | 2021-10-10 | 30 | 516d | 2021-09-11 | 0d |
|
Scheduled
|
2020-03-21 | 2020-04-13 | 24 | 526d | 2020-03-14 | +7d |
|
Scheduled
|
2018-09-15 | 2018-10-12 | 28 | 511d | 2018-09-15 | 0d |
|
Scheduled
|
2017-03-30 | 2017-04-22 | 24 | 22d | 2017-03-30 | 0d |
|
Unscheduled
|
2017-02-24 | 2017-03-08 | 13 | 504d | - | - |
|
Scheduled
|
2015-09-13 | 2015-10-09 | 27 | 508d | 2015-09-12 | +1d |
|
Scheduled
|
2014-03-22 | 2014-04-23 | 33 | 477d | 2014-03-22 | 0d |
|
Unscheduled
|
2012-11-28 | 2012-11-30 | 3 | 6d | - | - |
|
Scheduled
SGR/Major
|
2012-09-16 | 2012-11-22 | 68 | 531d | 2012-09-15 | +1d |
|
Scheduled
|
2011-02-27 | 2011-04-04 | 37 | 33d | 2011-03-05 | -6d |
|
Unscheduled
|
2011-01-21 | 2011-01-25 | 5 | 468d | - | - |
|
Scheduled
|
2009-09-06 | 2009-10-10 | 35 | 508d | 2009-09-05 | +1d |
|
Unscheduled
|
2008-04-14 | 2008-04-16 | 3 | 2d | - | - |
|
Scheduled
|
2008-03-02 | 2008-04-12 | 42 | 479d | 2008-03-01 | +1d |
|
Scheduled
|
2006-09-17 | 2006-11-09 | 54 | 515d | 2006-09-16 | +1d |
|
Unscheduled
|
2005-04-18 | 2005-04-20 | 3 | 2d | - | - |
|
Unscheduled
|
2005-04-15 | 2005-04-16 | 2 | 2d | - | - |
|
Scheduled
|
2005-03-02 | 2005-04-13 | 43 | 514d | 2005-03-01 | +1d |
|
Scheduled
|
2003-09-06 | 2003-10-05 | 30 | 378d | 2003-09-06 | 0d |
|
Unscheduled
|
2002-08-23 | 2002-08-24 | 2 | 150d | - | - |
|
Scheduled
|
2002-02-23 | 2002-03-26 | 32 | 220d | 2002-02-23 | 0d |
|
Unscheduled
|
2001-07-17 | 2001-07-18 | 2 | 243d | - | - |
|
Unscheduled
|
2000-11-16 | 2000-11-16 | 1 | 35d | - | - |
|
Scheduled
|
2000-09-02 | 2000-10-12 | 41 | 414d | 2000-09-02 | 0d |
|
Unscheduled
|
1999-07-16 | 1999-07-16 | 1 | 93d | - | - |
|
Scheduled
|
1999-03-13 | 1999-04-14 | 33 | - | 1999-03-13 | 0d |