Indian Point 2 - Status & History

Comprehensive reactor performance metrics, cycle analysis, and historical outage data.

Decommissioned

Permanently shut down on 2020-04-30. Outage statistics below reflect only the operating period. The final shutdown is not counted as an outage.
?
This unit is permanently shut down (shutdown date: 2020-04-30).
Shut Down
2020-04-30
?
Longest recorded period of continuous operation between outages (1999-10-13 to 2001-10-27).
745
Record Run
days
?
Breaker-to-Breaker runs — continuous operation exceeding the cycle-adjusted threshold (619 days for this 24-month cycle unit) with no trips to 0% power.
0
B2B Runs
?
Lifetime capacity factor: average power level across all recorded days (100% = always at full power).
82.7%
Capacity Factor
?
Total number of scheduled refueling outages detected in the historical data. D&D shutdown period excluded.
9
Outages
since 1999
?
Average time from first power generation (>0%) to sustained full power (≥95% for 2+ days) across the last 3 scheduled outages. Click to compare against the fleet on the Operator Efficiency Leaderboard.
8
Avg Startup
days (last 3)
?
Average fuel utilization — percent of the designed fuel cycle that this unit consumes before refueling, derived from the historical burn-down trajectory. Higher = more efficient operator (refuels with less margin remaining; closer to coastdown). Computed as 100% minus the unit's average refuel-point fuel %, using the last 3 years where available, otherwise lifetime average. Click to compare against the fleet on the Operator Efficiency Leaderboard.
92.9%
Fuel Utilization
lifetime avg
?
Duration of each outage in days, shown chronologically. Green bars are scheduled refueling outages, red bars are forced/unscheduled. The orange dashed line marks the average duration. Extended outages (>180 days) and D&D periods are excluded.

Outage Duration Trend

Indian Point 2 has 35 outages plotted here, averaging 14 days each. The most recent, in Apr 2019, was a unplanned outage lasting 2 days.
?
Days between consecutive scheduled refueling outage starts, showing operating cycle regularity. The purple dashed line marks the average cycle length. Most U.S. reactors operate on 18-month (547 day) or 24-month (730 day) cycles.

Cycle Length History

Between refueling outages, Indian Point 2 runs about 703 days, or roughly 23 months, per cycle. That average comes from 8 completed cycles, the most recent lasting 742 days.
?
Time in days from first power generation (>0%) to sustained full power (≥95% for 2+ consecutive days) after each scheduled refueling outage. The dashed line marks the average. Includes startup testing holds and power dips.

Startup Duration Trend

After a refueling outage, Indian Point 2 takes about 8 days to climb from first power back to full power. That average is drawn from 9 startups on record, and the most recent took 4 days.
?
Monthly capacity factor with outage events overlaid as red bands. Green bars show average power level per month. Toggle to Daily view for raw daily data.

Power History

Over its operating life, Indian Point 2 has run at about 82.7% of its rated capacity. Across the last 12 reported months it averaged 0.0%. On the chart, flat stretches near the top are full-power running and drops to zero are outages.
This table logs every recorded outage for Indian Point 2, 37 in all since 1999. Of those, 10 were scheduled refueling outages and 27 were unplanned or forced. The typical outage lasted about 35 days. Where the Scheduled column shows (Model), the date is a NukeWorker projection because the utility had not published one.
Scheduled Ext. Shutdown
2020-05-01 Decommissioned 1 (D&D) 393d 2020-03-17 +45d
Unscheduled
2019-04-03 2019-04-04 2 3d - -
Scram # 53954
2019-03-25 2019-03-31 7 3d - -
Scram # 53937
2019-03-16 2019-03-22 7 330d - -
Scheduled
2018-03-19 2018-04-20 33 87d 2018-03-18 +1d
Unscheduled
2017-12-09 2017-12-22 14 81d - -
Unscheduled
2017-09-19 2017-09-19 1 83d - -
Scram # 52829
2017-06-27 2017-06-28 2 355d - -
Scram # 52067
2016-07-07 2016-07-07 1 10d - -
Unscheduled
2016-06-25 2016-06-27 3 11d - -
Scheduled SGR/Major
2016-03-07 2016-06-14 100 91d 2016-03-07 0d
Scram # 51586
2015-12-06 2015-12-07 2 628d - -
Scheduled
2014-02-24 2014-03-18 23 374d 2014-02-14 +10d
Scram # 48750
2013-02-14 2013-02-15 2 321d - -
Scheduled
2012-03-05 2012-03-30 26 47d 2012-03-06 -1d
Scram # 47582
2012-01-11 2012-01-18 8 232d - -
Unscheduled
2011-05-21 2011-05-24 4 179d - -
Unscheduled
2010-11-08 2010-11-23 16 56d - -
Unscheduled
2010-09-04 2010-09-13 10 147d - -
Scheduled
2010-03-10 2010-04-10 32 57d 2010-03-23 -13d
Unscheduled
2010-01-12 2010-01-12 1 69d - -
Unscheduled
2009-11-03 2009-11-04 2 213d - -
Unscheduled
2009-04-04 2009-04-04 1 350d - -
Scheduled
2008-03-24 2008-04-19 27 494d 2008-03-25 -1d
Unscheduled
2006-11-16 2006-11-16 1 84d - -
Unscheduled
2006-08-24 2006-08-24 1 98d - -
Scheduled
2006-04-19 2006-05-18 30 514d 2006-04-18 +1d
Scheduled
2004-10-23 2004-11-21 30 51d 2004-10-22 +1d
Unscheduled
2004-09-01 2004-09-02 2 383d - -
Unscheduled
2003-08-15 2003-08-15 1 10d - -
Unscheduled
2003-08-04 2003-08-05 2 97d - -
Unscheduled
2003-04-29 2003-04-29 1 154d - -
Scheduled
2002-10-26 2002-11-26 32 302d 2002-10-26 0d
Unscheduled
2001-12-27 2001-12-28 2 54d - -
Unscheduled
2001-10-27 2001-11-03 8 300d - -
Unscheduled
2000-02-16 2000-12-31 320 126d - -
Unscheduled
1999-09-01 1999-10-13 43 - - -