Callaway

Refueling Outage · Day 26

Ameren Missouri·Fulton, MO·PWR·1,190 MWe

Live reactor status, daily power data, outage history & performance charts, scram history, capacity factor & statistics, community ratings, technical specifications, NRC licensing data, photos, nearby jobs, satellite map, contact information, and per diem rates for Callaway.

?
Composite Operational Excellence Score (0-100) — average percentile rank across 7 dimensions in three sub-scores: Reliability (capacity factor, forced outage days, B2B avg streak), Efficiency (fuel utilization, refuel duration), and Discipline (startup duration, scram count). 5-year window. Higher = more operationally excellent. Click to see the full breakdown.
   
Excellence
Rank locked · 93 units
Subscribers
?
Current reactor power level from the most recent NRC daily report.
0%
Power
OFFLINE (14 Days)
?
Days of continuous operation since the last outage ended. Ranked against all operating units.
--
Current Run
offline
?
Longest recorded period of continuous operation between outages.
528
Record Run
days
#87 of 95
Bottom Quartile
?
Breaker-to-Breaker runs — continuous operation exceeding the cycle-adjusted threshold (445 days for this 18-month cycle unit) with no trips to 0% power.
5
B2B Runs
#39 of 86
Mid Quartile
?
Lifetime capacity factor: average power level across all recorded days (100% = always at full power). Ranked against all NRC-tracked units.
85.6%
Capacity Factor
#85 of 95
Bottom Quartile
?
Net electricity actually generated over the most recent 12 months reported by the U.S. Energy Information Administration (Form EIA-923). These are authoritative actuals, not an estimate.
10.09 TWh
Net Generation
EIA-923 · 12 mo to 2026-07
?
Total NRC-reported scram events (emergency reactor shutdowns). Ranked fleet-wide — fewer scrams = better rank.
9
Scrams
#68 of 94
Mid Quartile
?
Years since commercial operation began. License remaining: 18 years.
41.8
Operating Age
years
18 yrs remaining

Excellence Score, Records & Plant Facts

About This Site

?
Written by NukeWorker from public records: facts that do not change. Operator, status and capacity come from the live data elsewhere on this page. Sources: Wikipedia: Callaway Nuclear Generating Station.

Callaway Energy Center is a single-unit nuclear plant in Callaway County, Missouri, in Auxvasse Township near Fulton, about five miles from the Missouri River, which supplies its cooling water.

Read more

Construction began on September 1, 1975. The plant has a Westinghouse four-loop pressurized water reactor, one of two built to the SNUPPS standard design, with a General Electric turbine-generator. It was first connected to the grid on October 24, 1984, and entered commercial operation on December 19, 1984. In July 2008 the owner applied for a license for a second unit, a 1,600-megawatt Areva EPR, and withdrew the proposal in April 2009.

10 miles southeast of Fulton, Missouri Forum Lodging tips

Facility Statistics

?
Key performance and lifecycle metrics calculated from NRC operational data. Includes operating age, construction timeline, capacity factor, efficiency, generation totals, and reliability records.
Callaway has operated for about 41.8 years and averaged a 85.6% lifetime capacity factor, generating roughly 253.7 TWh of electricity. Its longest unbroken run reached 528 days.
Lifecycle & Tenure
Operating Age: 41.8 Yrs
Build Time: 8.7 Yrs
Lic. Remaining: 18 Yrs
Production & Power
Lifetime CF: 85.6%
Efficiency: 33.4%
Generated: 253.7 TWh
Reliability & Outages
Record Run: 528 Days
Refuelings: 19
Avg Startup: 4.6 Days

Ownership & Construction

?
The utility or company that owns and operates the facility, the architect-engineer responsible for plant design, and the primary construction contractor. Click names to view all facilities by that entity on the map.
Owner/Operator: Ameren Missouri
Architect Engineer: BECH
Constructor: DANI
Ownership, operation and management history
No change of owner, operator or management company on record. Our history starts in 1999.
AEE Ameren Corporation NYSE
$106.63 ▲ +0.40 (+0.38%)
Previous Close 106.23
Day's Range 106.28 – 106.96
52-Week Range 96.57 – 118.32
Volume 1,419,565
Delayed quote as of Oct 21, 2026 3:55 PM ET. Source: Yahoo Finance. Full quote on Yahoo Finance

Operational Excellence Score Subscribers

Callaway is rated 0 to 100 on how well it actually runs, scored against every other operating reactor in the US fleet from its own operating record. Subscribers see the score, the three sub-scores behind it, and each of the seven measured inputs.

  • This unit's composite score and fleet rank
  • Reliability, Efficiency and Discipline sub-scores
  • All seven measured inputs, with fleet percentiles
  • Rank against comparable units, not just the fleet
  • Three-year, five-year and lifetime windows
  • Five-year trend, and every other operating US reactor

Included with every outage subscription and with NukeWorker Gold membership. Trading the outage rather than working it? The same record, cut by power market, is on NukeGryd.

Technical Specs

?
Reactor design specifications including type (PWR/BWR), containment design, nuclear steam supply system manufacturer, thermal and electrical power ratings, and current operational status.
Reactor Type: PWR
Containment: PWR-DRYAMB
NSS Supplier: WEST 4LP
Turbine Supplier: GENERAL ELECTRIC CO. IAEA
Thermal Power: 3565 MWt
Net Capacity: 1190 MWe
Gross Capacity: 1,275 MWe IAEA
Design Capacity: 1,171 MWe IAEA
Efficiency: 33.4%
Status: Operating
Lifetime Output: 360.9 TWh through 2025 IAEA

Licensing

?
NRC licensing history including docket number, license type and number, construction permit date, operating license issuance, commercial operation date, license renewal, and expiration date.
Docket #: 05000483
License #: NPF-30
License Type: OL-FP
Const. Permit: 1976-04-16
Construction Start: 1975-09-01 IAEA
Operating Lic: 1984-10-18
First Criticality: 1984-10-02 IAEA
Grid Connection: 1984-10-24 IAEA
Commercial Op: 1984-12-19
License Renewed: 2015-03-06
License Exp: 2044-10-18

Market & Region

?
EIA market and grid-region classifications: NERC reliability region, U.S. Census region, balancing authority responsible for grid operations, and whether the unit operates as a rate-regulated utility or a competitive merchant generator. Hover any value for the full name.
NERC Region: SERC — SERC Reliability Corporation
Census Region: WNC — West North Central
Balancing Authority: MISO — Midcontinent Independent System Operator (ISO/RTO)
Market Structure: Regulated — Rate-regulated utility (cost-of-service pricing)